HIGHLIGHTS FOR THE FIRST QUARTER 2011
-Production of 267,368 per gold equivalent ounce at cash costs of $14/GEO
-Gold production of 221,489 ounces
-Silver production of 2.3 million ounces Generated cash margin of $1,373 per ounce
-Significant financial and operational increases over the first quarter of 2010
-Production increased 11% to 267,368 GEO with record production from El Penon
-Revenues up 37% to $476 million Net earnings up 11% to $0.20 per share
-Adjusted earnings(1) up 110% to $0.21 per share
-Cash flow generated from operations(1) up 73% to $0.38 per share
-Cash balance increased to $460 million from $330 million, a 39% increase since 2010 year end
-Announced value enhancing deal with respect to Agua Rica with Xstrata and Goldcorp Yamana’s first quarter results continued to demonstrate our commitment to, and focus on, the delivery of predictable and reliable production and costs. We delivered production growth in the first quarter and record production from El Penon. Our cash costs continued to be one of the lowest in the industry commented Peter Marrone, Chairman and CEO. We continue to advance our new projects, the first of which, Mercedes, is expected to start production by the middle of 2012. C1 Santa Luz and Ernesto Pau-a-Pique will begin contributing by the end of 2012 and Pilar is expected to be in production in early 2013. All of the projects can be fully funded directly from our cash flow. These projects will contribute to our 60% production growth expected in the next three years.
FINANCIAL AND OPERATING SUMMARY
Revenues were $476 million in the first quarter from the sale of 208,135 ounces of gold, 2.3 million ounces of silver, and 29.7 million pounds of copper compared with $346 million in the same quarter of 2010. Sales quantities for the quarter were lower than production particularly in copper resulting in an increase in inventory at the end of the quarter which will positively impact earnings in the second quarter.
Adjusted Earnings were $152 million or $0.21 per share, an increase of 110%, in the first quarter of 2011 compared with $75.9 million or $0.10 per share in the same quarter of 2010.
Net earnings for the quarter were $148 million compared with net earnings of $132 million for the first quarter of 2010, which included earnings from discontinued operations of $7.4 million. Earnings per share were $0.20 on a basic and diluted basis for the first quarter of 2011, compared with basic and diluted earnings per share of $0.18 for the same quarter in 2010.
Cash flow generated from operations before changes in working capital were $282.3 or $0.38 per share compared with $163.1 million for the first quarter of 2010, which has been restated to reflect the composition of the revised measure for cash flows under IFRS.
The increase in cash flows generated from operations was primarily due to an increase in metal prices generating higher sales revenues, lower cash costs after credits and positive pricing adjustments for copper in concentrate.
Cash and cash equivalents as at March 31, 2011 were $460 million, representing an increase of $130 million since December 31, 2010.
In the three months ended March 31, 2011, production of gold equivalent ounces (GEO) totaled 267,368 compared with 239,838 GEO in 2010, representing a quarter-to-quarter increase of 11%.
In the first quarter, copper production of 38.5 million pounds from Chapada increased by 30% over production of 29.7 million pounds in the first three months of 2010.
dditionally, 7.1 million pounds of copper produced from Alumbrera were attributable to the Company in the first three months of 2011, compared to 11.8 million pounds in the same quarter of 2010.
For the quarter, by-product cash costs from operations were $14 per GEO, an 84% decrease from the $86 per GEO in the same period in 2010. By-product cash costs take into account the natural hedge of by-product metal prices for the Company’s production cost structure. By-product credits inherently offset mining inflation during periods of high metal prices. The Company believes that by-product cash costs are a better representation of its cost structure. Lower by-product cash costs compared to last year reflect strong cost containment and strong copper prices which mitigated cost pressures due to mining industry inflation and the appreciation of currencies in the countries where the Company’s mines are located.
Average co-product cash costs for the quarter were $449 per GEO. This compares to co-product cash costs of $423 per GEO for the quarter ended March 31, 2010. The increase in average co-product costs was mainly due to the strengthened exchange rates for the Brazilian Reais and Chilean Pesos.
Co-product cash costs per pound of copper were $1.21 for the quarter from Chapada, compared with $1.24 in the first quarter of 2010. Co-product cash costs per pound of copper including the Company’s interest in the Alumbrera mine, were $1.31 per pound of copper, compared with $1.14 for the same quarter in 2010.
OPERATING MINES
A summary of mine-by-mine operating results can be found on the final page of this press release.
Chapada, Brazil
Chapada produced a total of 33,392 ounces of gold in the first quarter compared with 27,794 ounces of gold in the same quarter of 2010, representing a quarter-over-quarter increase of 20%. Production of copper from Chapada of 38.5 million pounds was 30% higher than the production of 29.7 million pounds of copper during the comparable period in 2010.
Higher production of both gold and copper in the quarter compared with the first quarter of 2010 was mainly due to an increase in ore mined and ore processed. The Company began operating a new fleet of large trucks in the first quarter of 2010. Operating efficiency has developed since then with experience in operating the large trucks which has contributed to the increase in productivity. The Company also took measures to improve operating efficiencies during the rainy season compared to that of the prior year.
Subsequent to the quarter end, a $32.5 million shipment comprised of 11,000 tonnes of metal concentrate was made, which will positively impact second quarter earnings.
Production of gold and copper at Chapada in 2011 is expected to be in line with guidance.
By-product cash costs for the quarter were negative $2,615 per GEO, compared with negative $1,876 per GEO for the same quarter of 2010. Higher by-product cash costs credits reflect the continuous strength of copper prices resulting in lower by-product cash costs.
Co-product cash costs for the quarter were $286 per gold ounce and $1.21 per pound of copper which compared with $346 per gold ounce and $1.24 per pound of copper for the same quarter of 2010.
Jacobina, Brazil
Production at Jacobina was 30,319 ounces of gold in the first quarter, an increase of 21% from production of 25,022 ounces of gold in the first quarter of 2010. Higher production was mainly due to increased volume of ore mined and ore processed accompanied by improved grade and recovery rate.
The recovery rate at Jacobina for the first quarter was 93.5% compared to 91.9% for the first quarter of 2010. This is the result of the Company’s effort to modify the leaching cycle to improve recoveries which have trended upwards since the start-up of higher throughput levels. Gold grade for the quarter averaged 1.91 g/t also showing a 10% improvement over 1.73 g/t for the first quarter of 2010.
Production at Jacobina for 2011 is expected to be in line with guidance. Given the positive upward trend in production and the significant increase in mineral reserve grade, the Company will evaluate opportunities to increase production levels in 2011.
Cash costs averaged $611 per ounce of gold for the first quarter compared with $687 per ounce of gold in the first quarter of 2010, representing a quarter-over-quarter improvement of 11%. Cash costs progressively improved throughout the first quarter. The Company completed the first quarter with cash costs of $606 per ounce of gold in March, presenting a cost trend consistent with that of the prior year.
Fazenda Brasileiro, Brazil
The Fazenda Brasileiro mine produced 11,252 ounces of gold in the quarter ended March 31, 2011. This compares to 14,738 ounces of gold in the first quarter of 2010. Cash costs for the first quarter were $968 per ounce compared with $622 per ounce for the same period in 2010.
Production at Fazenda Brasileiro for 2011 is expected to be in line with guidance.
At Fazenda Brasileiro, the two new mineralization zones CLX2 and Lagoa do Gato, both discovered in 2009, are identified as having significant potential for high-grade sources of ore for the mill. Both infill and extension drilling confirm the continuity of mineralization in both areas. In 2011, the Company continues to develop the high-grade reserves at CLX2, and improve mine fleet costs using road trucks and focus on continuing to extend Fazenda Brasileiro’s mine life and lower costs. Improvement is expected and largely dependent on how quickly development of CLX2 can be advanced.
El Penon, Chile
El Penon had record quarterly production of 115,798 GEO during the first quarter of 2011. Production for the quarter consisted of 73,568 ounces of gold and 2.1 million ounces of silver, compared with 108,437 GEO, which consisted of 60,977 ounces of gold and 2.6 million ounces of silver produced in the first quarter of 2010. This represents a 7% quarter-over-quarter increase in 2011 versus 2010 production on a GEO basis.
Higher gold production was mainly due to improved gold grades and recovery rates compared with the same quarter of 2010. Higher gold grade areas including Al Este and Bonanza contributed to the increase in gold production. Since conversion to owner-mining, operational dilution has decreased and feed grade has improved. This, combined with increased capacity and the mining of higher grade veins including North Block area and Bonanza, has led to increased production. The decrease in silver production was primarily the result of mining lower planned silver grade areas, which was offset by improvements in gold.
GEO production at El Penon for 2011 is expected to be in line with guidance.
Cash costs were $397 per GEO in the quarter ended March 31, 2011, compared with $384 per GEO in the first quarter in 2010. The appreciation of the Chilean Peso was the main contributing factor to the increased cash costs. The average currency exchange rate of the Chilean Peso versus the United States Dollar went up by 9% from the first quarter of 2010.
Minera Florida, Chile
Minera Florida produced a total of 27,635 GEO in the current quarter compared with 20,630 GEO in the first quarter of 2010. The 34% quarter-over-quarter increase was mainly the result of higher volume of ore mined and ore processed and more effectively mining in narrower veins; production at Minera Florida for the first quarter of 2010 was interrupted as a result of the earthquake in Chile. Cash costs for the first quarter were $476 per GEO compared with $363 per GEO in the same quarter in 2010 due primarily to the appreciation of the Chilean Peso and mining inflation.
Gold grade for the quarter averaged 3.78 g/t which is lower than the 4.38 g/t for the first quarter of 2010. The lower gold grade was part of the mine plan for production from veins with better gold grade such as Tribuna and Victoria, which is expected to commence shortly.
Production at Minera Florida for 2011 is expected to be in line with guidance.
The Company’s expansion project at Minera Florida, which involves the processing of historic tailings, has advanced ahead of schedule. Completion is now planned for late 2011. Tailings re-processing is expected to contribute an additional 40,000 GEO per year for five years to current production at Minera Florida.
Gualcamayo, Argentina
Gualcamayo produced 37,597 ounces of gold in the first quarter compared with 29,462 ounces produced in the first quarter of 2010, representing a 28% quarter-over-quarter improvement.
Gold grade increased at Gualcamayo to 0.95 g/t from 0.89 g/t in the previous quarter and from 0.68 g/t in the first quarter of 2010. Gold recovery rate at Gualcamayo was 66.4% for the first quarter compared to 76% for the comparative quarter of 2010. The decrease in recovery is due to an increase in inventory residing on the pads and will normalize to an average yearly recovery rate expected to reach a sustainable 70% - 75%. The Company is taking steps to improve recoveries and minimize carbon fines as it progresses into Valle Norte later this year.
Production at Gualcamayo for 2011 is expected to be in line with guidance.
Cash costs were $507 per ounce in the quarter, compared with $443 per ounce in the first quarter of 2010. Management continued to reduce cash costs from the $662 per ounce level in the fourth quarter of 2010 down to the current level.
In 2011, the Company will focus on a number of operational initiatives, including efforts in sustaining the 1,500 tonne per hour feed through the mills, fleet expansion, underground development of QDD Lower West and expansion of heap leach pad at Valle Norte. In addition, the Company will continue to work on reducing reliance on contractors for increased cost predictability. Gold production for the second half of 2011 is expected to increase based on continuing higher grades, increases in crusher availability and throughput tonnage, and, by the end of the year, improved recovery at the new heap leach pad.
Alumbrera, Argentina
The Company’s interest in the Alumbrera Mine is accounted for as an equity investment. The Company recorded earnings from its 12.5% interest in Alumbrera Mine of $11.7 million for the three months ended March 31, 2011, similar to the earnings reported for the first quarter of 2010. The Company received $20.0 million in cash distributions during the three months ended March 31, 2011 compared with $12.9 million cash received in the first quarter of 2010.
Attributable production from Alumbrera was 11,374 ounces of gold and 7.1 million pounds of copper for the quarter. This compares with attributable production of 13,755 ounces of gold and 11.8 million pounds of copper for the first quarter of 2010.
Agua Rica, Argentina
The Company recently announced an agreement with Xstrata Queensland Limited and Goldcorp Inc. that would facilitate the ultimate integration of Agua Rica into Minera Alumbrera. Subject to Xstrata and Goldcorp exercising their option to have Alumbrera acquire the assets of Agua Rica, and following the integration of the projects, Xstrata, Goldcorp and Yamana would own interests in the combined project of 50%, 37.5% and 12.5% respectively, consistent with their current interest in Alumbrera.
In addition, the Company will receive a combination of initial and option payments and deferred consideration which allows Yamana to retain positive exposure to the majority of the significant gold resources at the Agua Rica project. The integration of Agua Rica with Alumbrera provides the greatest value potential for Yamana and the best opportunity for the development of Agua Rica in the Catamarca province of Argentina.
DEVELOPMENT PROJECTS UPDATE
Yamana has four development projects which are expected to commence production throughout 2012 and 2013 which are Mercedes, C1 Santa Luz, Pilar and Ernesto/Pau a Pique. Cumulatively, these projects will contribute an additional average annual production of 440,000 GEO.
Mercedes
The construction of Mercedes began in mid 2010 and is progressing as expected. During the quarter the mill was received on site. Concrete works and the first phase of the tailings dam development were almost completed. The bulk excavation and access roads were also completed. Mercedes is on track to be in production by mid 2012 with average annual production of 120,000 GEO.
Exploration at Mercedes continued to confirm the continuation and high grades of Lagunas Norte in the Barrancas system, increasing the strike length of the Barrancas zone to 1.1 kilometres. Development of Lagunas Norte has been accelerated to potentially enhance production levels at the project. Drilling also confirmed the continuation of significant widths within the Diluvio zone of the Lupita vein structure. The results of this exploration are expected to continue to increase and upgrade the total mineral resources at Mercedes. These new areas and additional exploration will provide additional accesses to the ore bodies. This increases the prospects that the Company will be able to increase production and extend mine life.
Pilar
Development at Pilar continued in the quarter with production expected to begin in the first quarter of 2013. Exploration confirmed mineralization along a 2.6 kilometre down dip extension of the current mineral resource. Northwest of the known Jordino deposit, lies the Ogo deposit: a hole drilled at depth confirmed mineralization below the previously interpreted footwall, significantly expanding potential in the 2.2 kilometres of untested strike length to the North. Additional exploration drilling suggests that growth in mineral reserves and mineral resources should continue in 2011.
The Pilar project is being built at a capacity level that is 30% higher than that contemplated in the feasibility study. The Company expects to utilize the increased capacity beginning in 2014. The Company expects to utilize the increased capacity beginning in 2014. Discovery of new resources along with the decision to advance Caiamar, a deposit located 38 kilometres from Pilar, to pre-feasibility assuming that ore would be processed at Pilar, is expected to support the higher capacity level. Studies have been completed confirming the processing plant at Pilar is suitable to process the Caiamar ore and the higher grades can offset the costs of transporting the ore. Resource development work has started at Caiamar, which could positively impact Pilar production rates as early as 2015.
C1 Santa Luz
Development at C1 Santa Luz continued in the quarter with the completion of all the engineering studies and construction start up. The project is planned initially as a conventional open pit with processing to be done through a carbon-in-leach (CIL) floatation circuit, which is on track to commence production in late-2012. Average annual production is expected to be approximately 100,000 ounces with production in each of the first two years expected to be approximately 130,000 ounces per year.
Ernesto/Pau-a-Pique
Construction at Ernesto/Pau-a-pique commenced in the first quarter advancing the project as expected. Ernesto/Pau-a-pique is planned as an underground and open pit operation with conventional processing through a gravity and CIL circuit. Annual production of approximately 100,000 ounces is expected to commence in late 2012. Exploration drilling has been initiated at Lavrinha, an adjacent area to Ernesto, targeted to increase mineable resources and the project mine life.
Jeronimo
Jeronimo is located in northern Chile approximately 30 kilometres south southwest of El Salvador at an elevation of 3,800 metres above sea level. The first mineral reserve estimate was declared of 1.6 million ounces, based on the pre-feasibility study recently completed on a fully consolidated basis. Based on the Company’s current ownership interest (57%), attributable mineral reserves are 0.93 million ounces. Approximately one third of the mineral reserves declared were a direct result of conversion from mineral resources via infill drilling. The Company is evaluating processing methods for better recoveries, which are anticipated to optimize the project economics. The Company will also be incorporating the impact of credits from the sale of manganese which was not included in the pre-feasibility, as well as the positive impact of other off-take products. The mineral resource remains open at depth and has potential to add significantly to resources.
Results of the evaluation of the different processing options and optimizations will be part of the feasibility study which is expected to be delivered by the end of 2011. The decision to proceed, after that time, will be based on continued positive results from a full feasibility and further consolidation of the ownership of Jeronimo, both of which are expected to occur.
OUTLOOK AND STRATEGY
The Company continues to focus on building sustainable and reliable gold production through optimizing existing operations, expanding current, near-term and in-development production plans, developing new operations and advancing its exploration properties. All of the Company’s operating mines are in known, stable jurisdictions in mining-friendly countries including Brazil, Chile, Argentina and Mexico. Three of the Company’s mines in development are in Brazil with the fourth new mine located in Mexico, adhering to the corporate strategy of pursuing growth in mining-friendly and stable jurisdictions. Through the steady path of organic growth and a disciplined approach in cost management, the Company expects to succeed in attaining its objectives set for the near-term and beyond.
The Company is maintaining the production and cost guidance previously stated in its January 11, 2011 press release.
Production is expected to be in the range of approximately 1.04 million to 1.14 million gold equivalent ounces in 2011. Annual silver production is expected at approximately 9 million ounces, and copper production is expected to be in the range of 145 million to 160 million pounds in 2011. In 2012, production growth continues as three development stage projects, including Mercedes, C1 Santa Luz, Ernesto/Pau-a-Pique, where construction decisions have already been made, increase production levels to between 1.2 . 1.32 million GEO in 2012, an overall increase of 27% from 2011.
Estimated cash costs for 2011 and 2012 are expected to be below $250 per GEO.
Production growth in 2013 is expected to increase by 60% from 2010 levels to between 1.46 and 1.68 million GEO with new contributions expected from Pilar, and full year production from Mercedes, C1 Santa Luz, and Ernesto/Pau-a-Pique.
These projects are advancing on schedule and are fully-funded from the Company’s available cash and cash flows generated from operations.
By 2014, production is targeted to be 1.7 million GEO, which represents production growth over four years of approximately 65% compared to 2010 production levels. This production includes production from existing mines and projects currently in development for which construction decisions have been made, and it does not include any additional production from new projects, expansions and optimizations under current evaluation.