Highlights:
· The 2010/11 infill and extension drilling campaign on the Cap-Oeste gold and silver deposit is now 95% complete and on target for finalising by the end of June. An NI 43-101 compliant resource update will then be completed, scheduled for reporting in Q3.
· Drilling on the E shoot located 150 metres south along strike from the Main shoot and within the Cap-Oeste deposit, continues to intersect high grade gold and silver, including 13.30 metres @ 8.58 grams per tonne (g/t) gold and 508 g/t silver in drill-hole CO-213. E shoot, together with the Main, B and C shoots, remains open at depth.
· Drilling will continue throughout the Austral winter months, aimed at extending the above shoots down plunge and further test the La Pampa, Tango and other prospects along the six kilometre strike extension of the Cap-Oeste Project.
The 2010/11 drilling campaign on the Cap-Oeste deposit was designed to infill a potential open pit area, 1,200m long x 150m depth on a 25m x 25m grid, and to extend the known shoots within the deposit area down plunge below the 150m level.
Results not previously reported include:
The El Tranquilo property block, covering over 80 square kilometres, is located approximately 120 kilometres to the south east of the Lomada de Leiva gold project where a heap leach operation is currently in progress. El Tranquilo contains Patagonia Gold's flagship project, Cap-Oeste, together with numerous other prospects including Monte Leon.