PDAC 2026SECCO ENCABEZADOgolden arrow
GLENCORE PACHON dia trabajador mineroMAPAL ENCABEZADO
WICHI TOLEDO ENCABEZADOWEG
VELADERO ENCABEZADO
KNIGHT PIÉSOLD ENCABEZADOSAXUM ENGINEERED SOLUTIONS ENCABEZADO
RIO TINTO LITHIUMWEG PINTURAS ENCABEZADOHIDROCONSTRUCCIONES
Milicic ENCABEZADOGLOBAL MINING ENCABEZADO
LITHIUM SOUTHGSB ROTATIVO MINING
OMBU CONFECATHIDROAR ENCABEZADO
ABRASILVER ENCABEZADORUCAPANELEPIROC ENCABEZADO
INFA ENCABEZADOCERRO VANGUARDIA
TELMECNEWMONT COVIDEXAR ENCABEZADO
INBELTCASUCCIArgentina lithium energy
SACDE ENCABEZADOEMERGENCIAS ENCABEZDODELTA MINING
AGUARTEC ECNABEZADOERAMET CABECERAPAN AMERICAN SILVER
FERMA ENCABEZADOMANSFIELD MINERA H
Proyectos
UPDATE DE CERRO MORO: EXTORRE VE UN PROYECTO MÁS PRODUCTIVO Y CON MAYOR VIDA ÚTIL. PERO TAMBIÉN SUBEN LOS COSTOS
05/08/2011

Minera Extorre eleva cálculos escala, costo proyecto argentino

Reuters

Extorre Gold subió el jueves las previsiones de producción para su proyecto de plata y oro Cerro Moro en Argentina, aunque también elevó sustancialmente la estimación del costo del proyecto.

La empresa minera de exploración con sede en Vancouver dijo que un nuevo estudio indica que Cerro Moro podría producir más o menos 495.000 onzas de oro y 26,6 millones de onzas de plata, en alrededor de 8 años.

Esto supera a su producción estimada previa de 436.000 onzas y 21,4 millones de onzas, respectivamente, registradas en el estudio del año pasado.

La escala mayor del proyecto también elevará gastos de capital y otros gastos por 60%.

El gasto de capital inicial subirá a alrededor de 209 millones de dólares, desde una proyección previa de 131 millones de dólares, mientras que Extorre ve un alza de costos de capital en el sitio a más de 50 millones de dólares, desde alrededor de 32 millones de dólares.

Además, si bien los costos mineros serían levemente más bajos que lo que se esperaba, la empresa ve una alza de 76% en los gastos de trituración y procesamiento, a 67 dólares por tonelada.

Extorre dijo que las alzas de costos de capital reflejan una actividad mayor en molinos, una flota minera más grande, una escalada de los costos materiales y otros costos que se incluyeron en el estudio previo.

La empresa dijo que los costos operativos más elevados incluyen costos de empleo más altos y otros factores.

Extorre scoping study of gold-silver mine in Argentina 'robust'

Mine-Web
Extorre Gold Mines beefed up the mine outline of its Cerro Moro gold-silver project in Argentina in a refreshed scoping study, garnering it one analyst's continued blessings.

"The results were in line with our estimates and confirm the robust nature of the project, which we believe is one of the highest margin development projects of a globally significant size owned by a junior mining company," wrote TD Securities mining analyst Daniel Earle in a research note to investors.

In the scoping study Extorre increased throughput by a third over its 2010 scoping study of Cerro Moro from 750 tonnes per day to 1,000 tonnes per day, while mine life stayed about the same at just over eight years.

Extorre boosted overall gold and silver production by 14 and 24 percent, respectively. The 1,000 tonne per day open pit and underground mine would churn out 494,700 ounces gold and around 27 million ounces silver over its operating lifetime.

But projected capital costs rose steeply to $201 million, 60 percent higher than those estimated in the 2010 Cerro Moro scoping study, as, among other things, Extorre said the larger mill throughput came with a higher pricetag.

Those higher capital costs, however, did not undercut Extorre's financial projections for Cerro Moro given that in the interim between this and the last scoping study gold and silver prices appreciated considerably.

Extorre now forecasts a $581 million net present value (NPV), pre-tax and without discount, and an undiscounted payback period of a year, in comparison to the previous $291 million undiscounted NPV and 1.8-year-long horizon to payback. Extorre assumed longterm, precious metal prices would average $1,320 per ounce gold and $26 per ounce silver in the latest economic outlook of Cerro Moro.

As previously reported on Mineweb, Extorre has also planned for a third scoping study that will look at up to a 1,500-tonne-per-day mining scenario and include resources from the as yet resource-undefined Zoe discovery, as well as expanded mineralization from other areas at Cerro Moro.

In anticipation of that Earle, with TD Securities, said, "We regard the Zoe discovery as being the best on the property and it took us about an hour from when the first three holes were released on April 19 (see our Action Note ‘Extorre has its Mariana Moment') to describe the discovery as being equivalent to the discovery of the Marianna veins made by Andean Resources that we believe precipitated attempts by Eldorado and Goldcorp to acquire the company - Goldcorp was ultimately successful in acquiring the company for $3.6 billion."

On news of the scoping study Extorre's shareprice had dropped 8 percent to C$11.60 as of presstime.

EL PRESS RELEASE

Extorre Announces Update to Cerro Moro Preliminary Economic Assessment 8 Year Mine Life +200,000 Oz/Yr. Gold Equivalent for First 3 Years

Extorre Gold Mines Limited is pleased to announce significant benefits for an expanded Cerro Moro project, as reported in a new Preliminary Economic Assessment

The new Study does not include mining of the recently discovered high grade Zoe vein or potential new resources from the Martina, Carla and Esperanza veins. An updated resource estimate that will include these veins is scheduled for release in Q4-2011.

PEA-2 contemplates an increased mining and ore processing rate of 1,000t ore/day (“tad”), up from 750tpd in the previous PEA, increased metal price assumptions (US$ 1,320/ounce gold and US$ 26/ounce silver) and the mining of all ore zones using a combination of open pit and underground methods. The Study is based on a NI 43-101 compliant mineral resource estimate completed in April, 2011 which included drilling completed on the Escondida, Loma Escondida, and Gabriela zones up until January, 2011.

Mining, processing and capital cost estimations used in PEA-2 have been completed to pre feasibility level or higher. PEA-2 is framed as a PEA to allow the inclusion of new inferred resources in a future study, PEA-3. PEA-2 was prepared by GR Engineering Services of Perth, Australia with input from leading industry consultants.

Highlights of PEA-2 include

-Total precious metal production of 494,700 ounces of gold and 26,600,000 ounces of silver over 8.25 years, based on mining and milling 1000t ore/day

-For the first 3 years, gold production averages 111,200 ounces/year plus silver production of 4.7 million ounces/year, for an average gold equivalent production of 206,300 ounces* per year. Average cash costs are $US 236 per ounce on a gold equivalent* basis.

-Initial capital (Direct costs): US$ 149.8 million + $US 25.7 million refundable VAT.

-Indirect capital costs (EPCM contract, Owners costs): US$ 32.8 million

-Pre-tax undercounted cash flow: $US 581 million

-Payback Period at a 0% discount rate: 12 months

PEA-2 is based on the following resources (see attached resource statement¹):

An Indicated Resource of 0.66 Mt (million metric tonnes) at 19 g/t gold (grams per metric tonne) and 835 g/t silver from the high grade Escondida and Loma Escondida vein zones, plus

Lower grade Indicated Resources from the Gabriela vein (0.53 Mt at 2 g/t gold and 371 g/t silver) and Inferred Resources of 1.86 Mt at 3.0 g/t gold and 182 g/t silver from the Escondida, Loma Escondida, Gabriela, Esperanza, and Deborah veins.