Vancouver, B.C., August 4, 2011 – Extorre Gold Mines Limited (TSX:XG, Frankfurt: E1R, OTC: EXGMF – “Extorre” or the “Company”) is pleased to announce significant benefits for an expanded Cerro Moro project, as reported in a new Preliminary Economic Assessment (“PEA-2”, or the “Study”).
The new Study does not include mining of the recently discovered high grade Zoe vein or potential new resources from the Martina, Carla and Esperanza veins. An updated resource estimate that will include these veins is scheduled for release in Q4-2011.
PEA-2 contemplates an increased mining and ore processing rate of 1,000t ore/day (“tad”), up from 750tpd in the previous PEA, increased metal price assumptions (US$ 1,320/ounce gold and US$ 26/ounce silver) and the mining of all ore zones using a combination of open pit and underground methods. The Study is based on a NI 43-101 compliant mineral resource estimate completed in April, 2011 which included drilling completed on the Escondida, Loma Escondida, and Gabriela zones up until January, 2011.
Mining, processing and capital cost estimations used in PEA-2 have been completed to pre feasibility level or higher. PEA-2 is framed as a PEA to allow the inclusion of new inferred resources in a future study, PEA-3. PEA-2 was prepared by GR Engineering Services of Perth, Australia with input from leading industry consultants.
Highlights of PEA-2 include
PEA-2 is based on the following resources (see attached resource statement¹):
It should be noted that this assessment is by definition preliminary in nature as it includes some mineral resources that are too speculative geologically to have the economic considerations applied to them that would enable them to be categorised as reserves at this time. As such there is no certainty that the preliminary assessment and project economics will be realised. A NI 43-101 Technical Report for the Cerro Moro PEA will be filed on SEDAR (www.sedar.com) and will be posted on the Company’s website at www.extorre.com
*Gold equivalent ounces are calculated by dividing the silver ounces by 50 and adding it to the gold value. **Silver equivalent ounces are calculated by multiplying the gold ounces by 50 and adding it to the silver value.
PEA Parameters
Parameters utilised in the 1,000tpd Cerro Moro PEA are indicated in the table below:
| Summary of Project Parameters | |
|---|---|
| Tonnes Ore Produced - Underground | 1,041,000t |
| Tonnes Ore Produced - Open Pits | 1,686,000t |
| Tonnes Waste Moved - Open Pits | 45,356,000t |
| Ore Processing Rate | 336,000t p.a. |
| Mine Life | 8.25 years |
| Gold Recoveries | 95% |
| Silver Recoveries | 87.4% |
| Total Gold Ounces Recovered | 494,700 oz |
| Total Silver Ounces Recovered | 26,600,000 oz |
| Total Gold Equiv* Ounces Recovered | 1,025,000 oz |
| Total Silver Equiv** Ounces Recovered | 51,400,000 oz |
| Initial Project CAPEX (Direct costs) | US$ 149.8M + US$ 25.7M VAT (recoverable) |
| Initial CAPEX (Indirect Costs) | US$ 33.6M (EPCM contract, owners costs, commissioning) |
| Sustaining Capital Life of Mine | US$ 52.7M (includes UG development, equipment replacement, mine closure) |
| Mining Costs – Open Pit | US$ 2.15/t |
| Mining Costs – Underground | US$ 45.91/t |
| Milling and Processing | US$ 67/t |
| G+A | US$ 7M/year |
| Cut-off Grades (Gold Equivalent*) | Open Pit 2 g/t, Underground 3.3 g/t |
| Refining + Transport + Insurance | US$ 10/oz gold, US$ 0.50/oz silver |
| Royalties / NSR’s | 5% Export Tax and new 1% Provincial Royalty on doré sales, 3% “Boca Mina”, 2% NSR (Cerro Vanguardia SA) |
Points of Comparison between this Study and the October 2010 PEA
Environmental Impact Assessment
The approved Environmental Impact Assessment (“EIA”) for the development of Cerro Moro contemplated mining 750t ore/day. An addendum to that EIA will be prepared following a PEA-3 study. The new study will include increased resources that include the development of the Zoe, Martina, Carla and Esperanza-Nini veins. The Santa Cruz Mines Ministry has indicated that the approval time for an addendum to an existing EIA is considerably shorter than that for a new EIA submission.
Current Engineering Activities
In addition to drilling, the Company will perform additional mining, geotechnical and metallurgical work on the new veins. Permitting for the many operational components of the project will also continue over the coming months. The Company expects that the next PEA will be able to consider a minimum 50% increase in both the mining and processing rates over those in this Study.
Qualified Persons Statement
Mr Bill Gosling, Senior Process Engineer of GR Engineering Services, Perth, Australia, and Mr. Eduardo Rosselot, Principal Mining Engineer of NCL Ltda., Santiago, Chile, are qualified persons as defined in NI 43-101 and have read and approved all technical portions of this release except for the mineral resource statement.
Mr David (Ted) Coupland, Director - Geological Consulting and Principal Geostatistician of Cube Consulting Pty Ltd, is a qualified person as defined in NI 43-101 and is responsible for preparing the April 2011 NI 43-101 compliant mineral resource statement.
Mr. Eric Roth, President and CEO of Extorre Gold Mines Ltd, is a qualified person as defined in NI 43-101 and is responsible for preparing the information contained in this news release.