Highlights
-- A long-term pumping test, located where the proposed extraction well
field will be located, has proved the feasibility of pumping at least 14
L/s from individual wells. Pumping rate was limited by pump size, not
aquifer conditions.
-- The well produced consistently high grade brine throughout the test,
with average lithium concentrations of 875+/-10 mg/L, 22% higher than
the adjacent diamond drill hole used in the resource estimate that gave
717+/-80 mg/L Li.
-- A 3D finite difference fluid flow and solute transport model that
incorporates variable density is currently being built and calibrated.
The model is intended to forecast production over the length of the
project life, and will be used to control the brine feed during
production.
-- Preliminary results from the model suggest that there are no unforeseen
difficulties in extracting the planned initial production of 16,400 tpa
lithium carbonate, with the possibility of subsequent increases in
production rates.
Orocobre Limited (TSX:ORL.TO - News)(ASX:ORE.AX - News) (the Company or Orocobre) announces the preliminary results of a long term pumping test on the Olaroz salar ("Olaroz Project") in Jujuy Province, North West Argentina.
Orocobre Managing Director, Richard Seville, stated, "With the results now available from the long term pumping test we can be confident that the proposed well field design will deliver the initial production capacity of 16,400 tpa lithium carbonate. The higher grade than anticipated, coupled with excellent flow rates, suggest the possibility of future project expansions."
The pumping test was located in the area of the proposed extraction well field and consistently produced brine with a Li concentration of 875+/-10 mg/L over 3 months at a flow rate of 14 L/s and a drawdown in the bore of 44 m. Interpretation of the data suggest that preferential flow is taking place to the well from specific geological units where the permeability and grade are higher. The information obtained will allow these specific units to be targeted during production. The flow rate was limited by the capacity of the pump, not by the well or aquifer, so that under production conditions average well flow rates may be expected to be significantly better than the design 15 L/s.
The results from the long term pumping test, together with the data on aquifer geometry, permeability, porosity, groundwater pressures, brine compositions, as well as the water balance incorporating rainfall and surface water inputs and evaporation outputs, obtained during the earlier drilling and testing phase, are being used by company consultant Dr Noel Merrick to build and calibrate a 3D finite difference model of fluid flow and solute transport that incorporates the known variation in fluid density across the salar. The model is being built using the well known and validated USGS Modflow-Surfact version 4, which is at the cutting-edge for this task. Dr Noel Merrick is a former Associate Professor at the National Centre for Groundwater Management at the University of Technology in Sydney.
The preliminary results from the model indicate that the cone of depression resulting from the well field pumping will be limited in extent and the grade will decline only slowly over the project life, well within the capacity of the solar ponds to ensure a consistent feed to the plant. The model will be used to forecast and control production throughout the project life, as well as to investigate potential production increases.
Richard Seville added, "The confirmation of pumping well design, capacity, and brine grade together with the preliminary model results represent another important step for the company towards production at Olaroz."
About Orocobre Limited
Orocobre Limited is listed on the Australian Securities Exchange and Toronto Stock Exchange (ASX:ORE.AX - News)(TSX:ORL.TO - News) and is the leading lithium-potash developer in the lithium and potassium rich Puna region of Argentina. For further information, please visit www.orocobre.com.
Orocobre Limited es uno de los productores de productos químicos de litio más grandes y económicos del mundo. La única compañía que cotiza en ASX produce productos químicos de litio de alto valor.
Tiene sede en Brisbane, Australia. El enfoque actual de la compañía está en las operaciones de extracción de litio y bórax en Argentina. Desde 2007, Orocobre Ltd. está registrada en el Australian Securities Exchange ASX y, a partir de 2010, figura en la TSX.