PDAC 2026SECCO ENCABEZADOgolden arrow
GLENCORE PACHON dia trabajador mineroMAPAL ENCABEZADO
WICHI TOLEDO ENCABEZADOWEG
VELADERO ENCABEZADO
KNIGHT PIÉSOLD ENCABEZADOSAXUM ENGINEERED SOLUTIONS ENCABEZADO
RIO TINTO LITHIUMWEG PINTURAS ENCABEZADOHIDROCONSTRUCCIONES
Milicic ENCABEZADOGLOBAL MINING ENCABEZADO
LITHIUM SOUTHGSB ROTATIVO MINING
OMBU CONFECATHIDROAR ENCABEZADO
ABRASILVER ENCABEZADORUCAPANELEPIROC ENCABEZADO
INFA ENCABEZADOCERRO VANGUARDIA
TELMECNEWMONT COVIDEXAR ENCABEZADO
INBELTCASUCCIArgentina lithium energy
SACDE ENCABEZADOEMERGENCIAS ENCABEZDODELTA MINING
AGUARTEC ECNABEZADOERAMET CABECERAPAN AMERICAN SILVER
FERMA ENCABEZADOMANSFIELD MINERA H
EXTORRE ANNOUNCES RESULTS OF CERRO MORO PRELIMINARY ECONOMIC ASSESSMENT- 9 YEAR MINE LIFE- 248,000 OZ/YR GOLD EQUIVALENT(I) FOR FIRST 5 YEARS
02/04/2012

Extorre Gold Mines Limited (TSX: XG.TO - News) (AMEX: XG - News) (Frankfurt: E1R.F - News) ("Extorre" or the "Company") is pleased to announce the results of Preliminary Economic Assessment #3 ("PEA", or the "Study") for the Cerro Moro gold-silver project in Santa Cruz province, Argentina.

The projected precious metal production over the life of the project is 848,000 ounces of gold and 47.2 million ounces of silver for a gold equivalent(i) production of 1.79 million ounces. Gold contributes approximately 48% of the projected revenue stream and silver 52%.

A number of different production scenarios were considered for this PEA, ranging from 1,000 tonnes per day ("tpd") to 1,500 tpd. The 1,150 tpd and 1,300 tpd scenarios were selected as being the most potentially viable throughput rates with respect to maintaining a consistent gold-silver stream from the current mineral resource. The economic modelling used a base case metal price assumption of US$1,320/ounce for gold and US$ 26/ounce for silver.

The 1,300 tpd is the preferred alternative due to the higher metal production in the early years. Further studies will continue to evaluate mining and scheduling options to enhance project economics. Exploration drilling will continue with the objective of discovering further high grade mineralization to replace lower grade material later in the production profile.

The PEA contemplates mining of mineralized zones using a combination of open pit (approx. 43%) and underground methods (approx. 57%). The study is based on the November 2011 mineral resource estimate for the Cerro Moro project by Cube Consulting ("Cube"). Mineral resources have been classified and reported in accordance with the CIM guidelines and National Instrument NI 43-101, Standards of Disclosure for Mineral Projects.

Projected Production Rates

 

--  Total metal production: 848,000 ounces of gold and 47.2 million ounces
    of silver (1.79 million ounces gold equivalent(i) or 89.6 million ounces
    silver equivalent(ii)).

--  Average production for first 5 years
    --  (at 1,300 tpd): gold equivalent production of 248,036 ounces(i) per
        year, comprising gold production of 123,017 ounces/year plus silver
        production of 6.251 million ounces/year.
    --  (at 1,150 tpd): gold equivalent production of 216,876 ounces(i) per
        year, comprising gold production of 109,985 ounces/year plus silver
        production of 5.344 million ounces/year.

--  Average life of mine production
    --  (1,300 tpd): gold equivalent production of 199,359 ounces(i) per
        year, comprising gold production of 94,270 ounces/year plus silver
        production of 5.254 million ounces/year.
    --  (1,150 tpd): gold equivalent production of 182,650 ounces(i) per
        year during the years of active mining, comprising gold production
        of 86,888 ounces/year plus silver production of 4.788 million
        ounces/year.

Projected Cost Summary

 

--  Average mine site cash costs: $303 per ounce on a gold equivalent(i)
    basis (first 5 years) at 1,300 tpd and $304 per ounce on a gold
    equivalent(i) basis (first 5 years) at 1,150 tpd.

--  Average cash costs, including royalties, refining and export tax (5%):
    $453 per ounce on a gold equivalent(i) basis (first 5 years) at 1,300
    tpd and $453 per ounce on a gold equivalent basis(i) (first 5 years)
    at 1,150 tpd.

--  Initial capital 1,300 tpd (Direct costs): $207.3M (incl. contingency)
    + $39.6M refundable VAT + Indirect capital costs (EPCM contract,
    Owners costs): $37.2 million

--  Initial capital 1,150 tpd (Direct costs): $185.1 M (incl.
    contingency) + $34.8M refundable VAT + Indirect capital costs (EPCM
    contract, Owners costs): $36.7 million

Initial capital expenditures (CAPEX) for the 1,300 tpd and 1,150 tpd mining / processing scenarios are estimated at US$ 284M and US$ 257M, including refundable VAT, respectively. Increases in the initial CAPEX costs are primarily attributable to an expanded project scale, increased underground development costs prior to the commencement of first commercial production, and the effect of inflation on all local construction costs.

Operating costs (OPEX) for open pit mining have increased to US$ 2.46/t and US$ 2.39/t for the 1,300 tpd and 1,150 tpd scenarios, respectively, in response to increased fuel, local labour costs and the effect of inflation on other costs. Average mine site cash costs during the first five years of commercial production are projected to be US$ 304 per gold equivalent ounce and US$ 313 per gold equivalent ounce for the 1,300 tpd and 1,150 tpd throughput rates, respectively.

Financial Summary

Utilizing metal prices of US$ 1320/oz. gold and US$ 26/oz. silver:

 

----------------------------------------------------------------------------
                                           1,300 tpd              1,150 tpd
----------------------------------------------------------------------------
Payback Period at 5% discount              24 months              22 months
----------------------------------------------------------------------------
Pre-tax IRR                                       63%                    66%
----------------------------------------------------------------------------
After tax IRR                                     47%                    47%
----------------------------------------------------------------------------
Pre-tax NPV (5% discount)          $737.4 million      $723.0 million
----------------------------------------------------------------------------
After Tax NPV (5% discount)          $463 million        $454 million
----------------------------------------------------------------------------

It should be noted that this assessment is preliminary in nature as it includes inferred mineral resources which are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the PEA will be realized.

A NI 43-101 Technical Report for the Cerro Moro PEA has been filed on SEDAR (www.sedar.com) and has been posted on Extorre's website at www.extorre.com

(i)Gold equivalent ounces are calculated by dividing the silver ounces by 50 and adding it to the gold value.

(ii)Silver equivalent ounces are calculated by multiplying gold ounces by 50 and adding it to the silver value.

PEA Parameters

Parameters utilized in the 1,300 tpd and 1,150 tpd cases are indicated in the table below:

 

----------------------------------------------------------------------------
Summary of Project
 Parameters                            1,300 tpd                  1,150 tpd
----------------------------------------------------------------------------
Tonnes Ore Produced -
 Underground                           2,288,000                  2,288,000
----------------------------------------------------------------------------
Tonnes Ore Produced -
 Open Pits                             1,747,000                  1,747,000
----------------------------------------------------------------------------
Tonnes Waste Moved -
 Open Pits                            52,652,000                 52,652,000
----------------------------------------------------------------------------
Ore Processing Rate
 (tonnes per year)                       448,000                    367,000
----------------------------------------------------------------------------
Mine Life                                9 years                 10.5 years
----------------------------------------------------------------------------
Gold Recoveries                               95%                        95%
----------------------------------------------------------------------------
Silver Recoveries                             93%                        93%
----------------------------------------------------------------------------
Total Gold Ounces
 Recovered                               848,000                    848,000
----------------------------------------------------------------------------
Total Silver Ounces
 Recovered                            47,290,000                 47,290,000
----------------------------------------------------------------------------
Total Gold Equiv.
 Ounces Recovered(i)                   1,794,000                  1,794,000
----------------------------------------------------------------------------
Total Silver Equiv.
 Ounces Recovered(ii)                 89,711,000                 89,711,000
----------------------------------------------------------------------------
Initial Project CAPEX     $207.3M + $39.6M     $185.1M + $34.9M
 (Direct costs)                              VAT                        VAT
                                (VAT recoverable)          (VAT recoverable)
----------------------------------------------------------------------------
Initial CAPEX                    $37.2M (EPCM            $36.7M (EPCM
 (Indirect Costs)              contract, owners'          contract, owners'
                            costs, commissioning)      costs, commissioning)
----------------------------------------------------------------------------
Sustaining Capital            $149M (includes         $167M (includes
 Life of Mine                        underground                underground
                          development, equipment     development, equipment
                            replacement and mine       replacement and mine
                                         closure)                   closure)
----------------------------------------------------------------------------
Mining Costs - Open       $2.46/t (average of     $2.39/t (average of
 Pit                               ore and waste)             ore and waste)
----------------------------------------------------------------------------
Mining Costs -
 Underground                         $50.06/t                $45.12/t
----------------------------------------------------------------------------
Milling and Processing               $73.32/t                $76.81/t
----------------------------------------------------------------------------
General and
 Administrative                         $20/t                   $20/t
----------------------------------------------------------------------------
Cut-off Grades (Gold           Open Pit 2.1 g/t,          Open Pit 2.1 g/t,
 Equivalent(i))              Underground 3.4 g/t        Underground 3.4 g/t
----------------------------------------------------------------------------
Refining + Transport + Insurance $10/oz gold, $0,5/oz silver $10/oz gold, $0,5/oz silver  
----------------------------------------------------------------------------
Royalties / NSR's          5% Export Tax and new      5% Export Tax and new
                           1% Provincial Royalty      1% Provincial Royalty
                         on dore sales, 3% "Boca    on dore sales, 3% "Boca
                            Mina", 2% NSR (Cerro       Mina", 2% NSR (Cerro
                                   Vanguardia SA)             Vanguardia SA)
----------------------------------------------------------------------------
Corporate Tax Rate                            35%                        35%
----------------------------------------------------------------------------

For more detailed information on mine design, financial modelling, resources and mine production scheduling used for this PEA, please follow this link to the attached PDF

Brief Description of the Project

Electrical power

Electrical power is expected to be supplied to the Project via a 132 kV line that will connect to the Argentine national grid at a point located approximately 60 km to the north-west of Puerto Deseado and near the locality of Antonio de Biedma.

Water

The water supply to the process plant and infrastructure will be provided from water bores located to the north and east of the plant site and adjacent to the Zoe prospect. A water treatment plant will be located at the plant site and will provide potable water for distribution to offices, amenities and the accommodation camp.

Mining

The mineralized zones will be mined by conventional open pit (surface) mining and underground methods. Underground mining will be a modified Bench and Fill method that utilizes a primary decline, spiral ramps and cross cuts to access the mineralized horizon. Mining levels are spaced 16 m apart with 12 m high stope benches.

Mineral Processing and Recovery Methods

The process design targeted simplicity consistent with maximising recovery of the precious metals and the utilization of well-established technologies. The comminution circuit design involves a three stage crushing circuit followed by a single stage closed circuit ball mill. Classifier overflow from the grinding circuit reports to a conventional flotation circuit to enhance recovery of gold and silver minerals for the subsequent concentrate regrind and leaching stages. The flotation tailings are to be thickened prior to being leached in a five stage leach circuit with a nominal residence time of 48 hours. The leach residue is to be washed in a 5 stage counter current decantation thickening circuit with precious metals recovered from the pregnant solution by a conventional Merrill Crowe circuit. The processing plant has been designed to treat 1,300 tpd of feed with maximum head grades of 25 g/t of gold and 1,000 g/t of silver.

Process tailings

The process tailings from the first two years of production will be stored in a cell to be built adjacent to the process plant. The cell will be equipped with a geosynthetic liner and facilities to reclaim and recirculate tailings. A larger tailings storage facility will be constructed after the mine commences production in a large shallow valley area with earth fill embankments providing the necessary enclosure. The facility will have a geosynthetic liner to prevent seepage into the groundwater system. After the first two years, the process tailings will be stored in this facility.

Environmental Impact Assessment

An Environmental Impact Assessment ("EIA") for a mine throughput of 750 tpd was approved by Santa Cruz provincial authorities in May, 2011. An addendum to that EIA will be prepared over the next 60 days. The Santa Cruz Mines Ministry has indicated that approval times for addenda to existing EIA's are considerably shorter than that for new EIA submissions.

Assessment Authors and Qualified Persons Statement

NCL Ingenieria y Construccion Ltda. was responsible for the compilation of information and preparation of the overall study. Significant contributions were also received from Cube Consulting and GR Engineering Services.

 

1.  Carlos Guzman, Mining Engineer (Registered Member of the Chilean Mining
    Commission), Principal and Project Director of NCL Ingenieria y
    Construccion Ltda. is a qualified person as defined in NI 43-101 and was
    responsible for the mining related studies and economic valuation;
2.  Bill Gosling, Senior Process Metallurgist, of GR Engineering Services
    Ltd (FAusIMM), is a qualified person as defined in NI 43-101 and was
    responsible for the information provided for the metallurgy and process
    plant design;
3.  David (Ted) Coupland (BSc DipGeoSc CFSG ASIA MAusIMM(CP) MMICA) Director
    - Geological Consulting - Principal Geostatistician, Cube Consulting Pty
    Ltd, is a qualified person as defined in NI 43-101 and was responsible
    for resource estimation, exploration, drilling and data verification;
4.  Anthony Sanford Professional Natural Scientist registered with the South
    African Council for Natural Scientific Professions, Environmental
    Services Manager for Ausenco Peru SAC, is a qualified person as defined
    in NI 43-101 and was responsible for the environmental and community
    sections
5.  Krishna Sinha Professional Engineer registered in the State of Utah,
    Corporate Technical Director for Ausenco Vector, is a qualified person
    as defined in NI 43-101 and was responsible for the sections relating to
    the Tailings Storage Facility
6.  Michael Gabora Professional Engineer Registered in the State of Utah,
    Senior Hydrogeologist for Ausenco Vector,is a qualified person as
    defined in NI 43-101 and was responsible for the hydrology and
    hydrogeology sections of the report

Mr. Eric Roth, President and CEO of Extorre Gold Mines Ltd, is a qualified person as defined in NI 43-101 and is responsible for preparing the information contained in this news release.

About Extorre

Extorre is a Canadian public company listed on the Toronto and NYSE Amex Exchanges under the symbol XG. The principal assets of the Company comprise CDN $37 million in cash and the Cerro Moro, Puntudo, and Falcon projects in Argentina.

Detailed engineering and development planning continue at Cerro Moro and an updated Environmental Impact Assessment is expected to be lodged with Santa Cruz mining authorities in the next few months.

Exploration with four drills continues at Cerro Moro, with the aim to increase the total resources on the property and to in-fill drill certain areas for mine planning purposes. Results from current drilling will be released as they are received.

You are invited to visit the Extorre web site at www.extorre.com.


Vuelva a HOME

*La información y las opiniones aquí publicados no reflejan necesariamente la línea editorial de Mining Press y EnerNews

CONTACTE AQUÍ
Teléfono/s
-
Rubros

KNIGHT PIESOLD DERECHA NOTA GIF 300
Lo más leído
PODER DE CHINA
NOTA MÁS LEIDAs MP GIF