TORONTO, April 24, 2013 — Barrick Gold Corporation (NYSE:ABX)(TSX:ABX) (Barrick or the "company") today reported strong first quarter 2013 financial and operating results.
| FIRST QUARTER 2013 OPERATING HIGHLIGHTS AND FULL YEAR 2013 GUIDANCE | ||||
| Gold | First Quarter 2013 | 2013 Guidance | (previous) | |
| Production (000s of ounces) | 1,797 | 7,000-7,400 | ||
| All-in sustaining costs ($ per ounce)(1) | 919 | 950-1,050 | (1,000-1,100) | |
| Total cash costs ($ per ounce)(1) | 561 | 610-660 | ||
| Copper | ||||
| Production (millions of pounds) | 127 | 480-540 | ||
| C1 cash costs ($ per pound)(1) | 2.46 | 2.10-2.30 | ||
| C3 fully allocated costs ($ per pound)(1) | 3.00 | 2.60-2.85 | ||
"Our high quality portfolio of mines combined with our sharp focus on cost management has translated into strong quarterly financial and operating results. It is very rewarding to see that our cost reduction efforts have begun to take effect and are reflected in low all-in sustaining costs of $919 per ounce and total cash costs of only $561 per ounce this quarter. We have also further reduced total capex, exploration and all-in sustaining cost guidance for the full year," said Jamie Sokalsky , Barrick's President and CEO. "At Pascua-Lama, we are working to address the environmental and other regulatory requirements on the Chilean side of the project. Concurrently, we are taking a hard look at evaluating all alternatives in light of the uncertainties associated with the suspension of construction in Chile. We are committed to a disciplined approach to capital allocation, based on the principle that returns will drive production, production will not drive returns. While we remain positive on the long-term fundamentals for gold and copper, we don't rely on higher metal prices to be the only driver of shareholder returns." Net earnings and adjusted net earnings for the first quarter 2013 of $847 million ($0.85 per share) and $923 million ($0.92 per share), respectively, compared to net earnings and adjusted net earnings of $1.04 billion ($1.04 per share) and $1.10 billion ($1.10 per share), respectively, in the same prior year period. The decrease in net earnings and adjusted net earnings was largely driven by lower realized gold and copper prices, lower gold and copper sales volumes and higher cost of sales applicable to gold and copper, partially offset by lower income tax expense. Significant adjusting items (net of tax effects) for the quarter include: First quarter 2013 operating cash flow of $1.09 billion compares to $1.37 billion in the first quarter of 2012. Adjusted operating cash flow of $1.16 billion removes the impact of the Australian dollar hedge settlement and compares to adjusted operating cash flow of $1.48 billion in the same prior year period. First quarter 2013 gold production was 1.80 million ounces at all-in sustaining and total cash costs of $919 per ounce and $561 per ounce, respectively. All-in sustaining and total cash costs benefited from strong performances at Goldstrike, Cortez, and Veladero. The company reaffirms 2013 gold production guidance of 7.0-7.4 million ounces at total cash costs of $610-$660 per ounce. Full year all-in sustaining cost guidance has been reduced to $950-$1,050 per ounce from the previous guidance of $1,000-$1,100 per ounce. North America Regional Business Unit North America produced 0.87 million ounces at all-in sustaining and total cash costs of $770 per ounce and $487 per ounce, respectively. Barrick's 60 percent share of production from the new Pueblo Viejo mine was 96,000 ounces at total cash costs of $550 per ounce, after achieving commercial production in January. The mine remains on track to ramp up to full capacity in the second half of this year. Barrick's share of average annual gold production in the first full five years of operation is anticipated to be 0.625-0.675 million ounces at all-in sustaining and total cash costs of $500-$600 per ounce(2) and $300-$350 per ounce(2), respectively. The government of the Dominican Republic is asking Pueblo Viejo Dominicana Corporation (jointly owned 60 percent by Barrick and 40 percent by Goldcorp) to accelerate and significantly increase its share of the benefits from Pueblo Viejo. The company, while reserving its rights under the Special Lease Agreement (SLA), which cannot be unilaterally altered, continues to engage in dialogue with the government in an effort to achieve a mutually acceptable outcome. The Cortez mine produced 0.34 million ounces at total cash costs of $177 per ounce, largely reflecting better than anticipated grades. Goldstrike produced 0.23 million ounces at total cash costs of $605 per ounce primarily as a result of higher than expected grades and recoveries. We continue to expect full year 2013 production for North America to be 3.55-3.70 million ounces at all-in sustaining and total cash costs of $820-$870 per ounce and $495-$545 per ounce, respectively. South America Regional Business Unit South America produced 0.37 million ounces at all-in sustaining and total cash costs of $638 per ounce and $405 per ounce, respectively. Higher silver by-product credits at the Veladero mine and delays in sustaining capital spend at Pierina and Veladero positively impacted all-in sustaining costs. The Veladero mine contributed 0.21 million ounces at total cash costs of $400 per ounce and Lagunas Norte produced 0.15 million ounces at total cash costs of $333 per ounce. We continue to expect South America to produce 1.25-1.35 million ounces in 2013 at all-in sustaining and total cash costs of $875-$925 per ounce and $550-$600 per ounce, respectively. Australia Pacific Regional Business Unit Australia Pacific produced 0.45 million ounces at all-in sustaining and total cash costs of $1,096 per ounce and $785 per ounce, respectively. Porgera, the region's largest contributor, produced 0.12 million ounces at total cash costs of $934 per ounce, reflecting the processing of lower cost stockpiles. We continue to expect full year 2013 production for Australia Pacific to be 1.70-1.85 million ounces at all-in sustaining and total cash costs of $1,200-$1,300 per ounce and $880-$950 per ounce, respectively. African Barrick Gold plc First quarter attributable production from African Barrick Gold was 0.11 million ounces at all-in sustaining and total cash costs of $1,561 per ounce and $931 per ounce. We continue to expect Barrick's share of 2013 production from African Barrick Gold to be 0.40-0.45 million ounces at all-in sustaining and total cash costs of $1,550-$1,600 per ounce and $925-$975 per ounce, respectively. Global Copper Business Unit Copper production was 127 million pounds at C1 cash costs of $2.46 per pound and C3 fully allocated costs of $3.00 per pound. Lumwana produced 57 million pounds at C1 cash costs of $3.41 per pound and Zaldívar produced 70 million pounds at C1 cash costs of $1.54 per pound. We continue to expect 2013 copper production to be 480-540 million pounds at C1 cash costs of $2.10-$2.30 per pound and C3 fully allocated costs at $2.60-$2.85 per pound. Utilizing option collar hedging strategies, the company has protected the downside on approximately half of our remaining 2013 copper production at an average floor price of $3.50 per pound and can participate on the same amount up to an average price of $4.25 per pound(3). Pascua-Lama is one of the world's largest gold and silver resources with nearly 18 million ounces of proven and probable gold reserves(4), 676 million ounces of silver contained within the gold reserves(4), and an expected mine life of 25 years. It is expected to produce an average of 800,000-850,000 ounces of gold and 35 million ounces of silver in its first full five years of operation at all-in sustaining and total cash costs of $50-$200 per ounce(5) and negative $150 to $0 per ounce, respectively. During the fourth quarter of 2012, pre-stripping activities in Chile were halted to address increased dust in the open pit area following stronger than normal winds. The project has since strengthened dust mitigation and control measures. Regulatory restrictions have also been placed on the project due to the need to repair and improve certain aspects of the water management system in Chile. Completion of measures to address these aspects is targeted for first quarter 2014. On April 9, 2013, the Copiapó Court of Appeals in Chile granted a request for a preliminary injunction to suspend construction activities on the Chilean side of the project pending a hearing on a constitutional rights action filed in September of 2012. The action alleges noncompliance with the environmental requirements of the project's Chilean environmental approval. Upon confirming the court order, Barrick took immediate steps to suspend construction activities in Chile, which includes work on the primary crusher and the Chilean side of the tunnel that conveys ore from Chile to Argentina. Activities determined to be necessary for environmental protection are expected to continue, upon appropriate authorization as contemplated by the Court. Construction in Argentina, where the majority of Pascua-Lama's critical infrastructure is located, including the process plant and tailings storage facility, has not been affected. Until we have clarity on the regulatory and legal aspects, we are unable to fully assess the impact on the capital budget, operating costs and schedule of the project. The company is at an early stage of evaluating an alternative development plan that involves accelerating the development of another smaller pit in Argentina in order to provide a source of ore for initial production. This alternative could provide ore for about six months of production during commissioning and ramp up, following which the mine plan would be dependent on a continuous supply of Chilean ore. Therefore, if resumption of construction activities in Chile, including the pre-stripping, is delayed beyond late 2013, or if such development alternative is determined not to be feasible, there could be a significant change to the mine plan and an impact on the capital cost and production schedule of the project. The company will continue to evaluate all alternatives, in light of the uncertainties associated with the legal and regulatory actions, and the current commodity price environment, including the possibility of suspending the project. As of March 31, 2013, approximately $4.8 billion had been spent. During the quarter, the La Mesa substation in Chile was energized and the southern portion of the 23Kv mine distribution loop completed. As of that date, the tunnel was approximately 80 percent complete. In Argentina, construction of the process plant facility advanced with about 70 percent of structural steel erected; 65 percent of concrete poured; and 55 percent of mass earthworks completed. Barrick's strategy prioritizes shareholder value creation by focusing on maximizing risk-adjusted rates of return and free cash flow. The company has taken and will undertake the following steps to re-focus the business and adhere to the principles of its disciplined capital allocation framework based on the principle that returns will drive production, production will not drive returns:FINANCIAL RESULTS
OPERATING RESULTS
PASCUA-LAMA PROJECT UPDATE
DISCIPLINED CAPITAL ALLOCATION
Barrick's vision is to be the world's best gold mining company by operating in a safe, profitable and responsible manner. Barrick's shares are traded on the Toronto and New York stock exchanges.
Barrick busca ser la empresa de minería de oro más valorada del mundo al descubrir, desarrollar y retener los mejores activos, con las mejores personas, para entregar ganancias sostenibles para propietarios y aliados.
Actualmente tiene operaciones y proyectos mineros en 15 países, incluyendo Argentina, Australia, Canadá, Chile, Costa de Marfil, República Democrática del Congo, República Dominicana, Malí, Papúa Nueva Guinea, Perú, Arabia Saudita, Senegal, Estados Unidos y Zambia.
En Chile, Barrick está presente con los proyectos Pascua-Lama y Norte Abierto, la mina de cobre Zaldívar, el proceso activo de cierre de la mina El Indio, además del proyecto de exploración Alturas.
Las acciones de la Compañía cotizan en la Bolsa de Nueva York con el símbolo GOLD y en la Bolsa de Toronto con el símbolo ABX
Presidente del Directorio Barrick: John L. Thornton
Presidente y Director Ejecutivo de Barrick: Mark Bristow
Director Ejecutivo Barrick Argentina & Chile: Marcelo Álvarez
Gerente General de Veladero: José Quiñones
Desde 2005 en Argentina opera la mina Veladero que ha aportado unos 9.500 millones de dólares a la economía argentina a través de impuestos, regalías, salarios y pagos a proveedores locales. La operación es un Joint Venture con Shandong Gold