AngloGold Ashanti Limited
7 August 2013
AngloGold Q2 Operating Results Solid; Plans Overhead Savings up to $482m
- Solid gold production of 935koz, in-line with guidance provided for the period of 900-950k oz; up 4% from Q1.
-Total cash costs of $898/oz, better than the adjusted guidance range for the period of $900/oz and $920/oz.
- $1.25bn bond issue provides additional liquidity; improves debt maturity profile.
- Net debt at 30 June 2013 was $2.78bn, reflecting a net debt to EBITDA ratio of 1.56 times.
- Capital expenditure for 2013 reduced from $2.1bn to $1.95bn-$2.0bn.
- Tropicana is ahead of schedule and remains within budget; commissioning underway.
- Kibali is progressing well and remains on budget and on schedule for production as early as October.
-No second-quarter dividend declared given volatile environment; dividend to be reviewed at year-end resumption to bi-annual dividend schedule.
-All Injury Frequency Rate (AIFR) in the quarter was 7.61 per million hours worked, 11% year-on-year improvement.