Vancouver, Canada
Silver Standard Resources Inc
9 October, 2013
Silver Standard Resources Inc. (NASDAQ: SSRI) (TSX: SSO) (the "Company") provides its third quarter 2013 operational update for the Pirquitas Mine in Jujuy, Argentina.
Third Quarter 2013 Operating Highlights:
• Delivered consistent silver production and sales: Produced and sold 2.0 million ounces of silver.
• Produced record 7.8 million pounds of zinc: Third quarter zinc production represented a 40% quarter-on-quarter improvement due to higher zinc grades and plant recoveries.
• Focused on operating performance: Managed operating variation from blended ore mix to achieve stable silver recoveries and mill throughput of 4,283 tonnes per day, on average, 7% above nominal design.
"Pirquitas continues to advance through the pit phase transition and the production result for this quarter was achieved notwithstanding ore blend variety presented to the plant," said John Smith, President and CEO. "At this point in the economic cycle, reducing costs and driving margin is the priority at Pirquitas. Therefore, achieving this production result, given the cost priority, underlines the determination to drive performance at the Mine."
Summary of Mine Operating Statistics
|
|
|
Q3 2013 |
Q2 2013 |
% Change |
|
Total material mined |
Kt |
4,465 |
4,471 |
(0.1%) |
|
Ore milled |
Kt |
394 |
365 |
7.9% |
|
Silver mill feed grade |
g/t |
215 |
216 |
(0.5%) |
|
Zinc mill feed grade |
% |
1.91 |
1.53 |
24.8% |
|
Silver recovery |
% |
74.6 |
74.8 |
(0.3%) |
|
Zinc recovery (zinc concentrate) |
% |
47 |
46 |
2.2% |
|
Silver produced |
'000 oz |
2,028 |
1,890 |
7.3% |
|
Zinc produced (zinc concentrate) |
'000 lbs |
7,818 |
5,589 |
39.9% |
|
Silver sold |
'000 oz |
1,969 |
2,207 |
(10.8%) |
|
Zinc sold (zinc concentrate) |
'000 lbs |
4,952 |
2,217 |
123.4% |
Note: Percent changes are calculated using the rounded numbers presented above.
Mine Operations
The Pirquitas Mine produced 2.0 million ounces of silver during the third quarter of 2013, higher than the 1.9 million ounces produced in the second quarter of 2013. The increase in silver production reflects planned higher tonnage through the mill. In the first three quarters of 2013, the Mine produced 5.9 million ounces of silver. During the third quarter, the Company sold 2.0 million ounces of silver, in line with production.
The Mine also produced 7.8 million pounds of zinc in zinc concentrate in the third quarter, a 40% quarter-on-quarter improvement and the highest quarterly zinc production result in the history of the Mine to date. This record zinc production reflects higher zinc grades, as the Company mined more of the zinc-rich Potosi area of the San Miguel open pit, combined with improved recoveries.
Approximately 394,000 tonnes of ore were milled during the third quarter of 2013, compared to 365,000 tonnes in the second quarter of 2013. Ore was milled at an average rate of 4,283 tonnes per day, 7% above the mill's nominal design. This compares to an average milling rate of 4,009 tonnes per day in the second quarter. Ore milled contained an average silver grade of 215 g/t, compared to 216 g/t reported in the second quarter. The average recovery rate for silver decreased marginally to 74.6% from 74.8% in the previous quarter, mainly due to more oxidized and transitional ore in the mill feed. As Phase 2 of the San Miguel open pit deepens, the proportion of sulphide ore in the mill feed is expected to increase.
Third Quarter Earnings Release
The Company plans to issue its third quarter earnings release on Tuesday, November 5, 2013 after markets close.
Qualified Person
The scientific and technical data contained in this news release has been reviewed and approved by the following Qualified Person ("QP") under National Instrument 43-101, who consents to having his name included in this news release.
• Andrew W. Sharp, BEng., FAusIMM: Mr. Andrew W. Sharp, who has been employed by the Company as Vice President, Technical Services since September 2011, is the QP responsible for the technical content of this news release.
Silver Standard Resources es una compañía canadiense que se dedica a la exploración, desarrollo y producción de sus propiedades de recursos con predominio de plata. El enfoque de la minera está en optimizar la producción de plata en su mina Pirquitas en Argentina, y en avanzar otros proyectos de exploración y desarrollo, incluyendo Pitarrilla y San Agustín en México, el proyecto de oro y plata San Luis en Perú y Diablillo en Argentina.